Which of the following is considered the base of the standard and guide for the project management?

(A) Prescriptive practices
(B) Descriptive practices
(C) Both (A) & (B)
(D) None of these

The answer is: (B) Descriptive practices
Project management standard and guide are both based on descriptive practices rather than prescriptive practices.