I. It brings change
II. It has risk
III. The outcome is certain
(A) I only
(B) II only
(C) I and II only
(D) I, II, and III
The answer is: (C) I and II only
The outcome of a project is not certain. There is an element of risk in a project.
I. It brings change
II. It has risk
III. The outcome is certain
(A) I only
(B) II only
(C) I and II only
(D) I, II, and III
The answer is: (C) I and II only
The outcome of a project is not certain. There is an element of risk in a project.